[Gasification] Wood Gasifier Alaska, Q & A

Greg Manning a31ford at inetlink.ca
Sun Feb 25 20:07:52 CST 2007



 Ken,

 First off, I guess you are right, the stuff I would have consumed, is, "at
going rate" and what I "under base load", "Export"  is about a 2 to 1 (Give
or take).  (I need to export 2Kw to buy 1 Kw later, during the summer when I
shut down, and would "break-even" at that).

I could generate through the summer, and always turn a profit, however, then
the engine's life would be reduced to 2 years (25,000 miles is roughly 2-1/2
weeks of operation).

 Approx 744 hours to a month, 8760 to a year, if you said "60 miles an hour"
8760 x 60 =  525600 miles a year @ 1800 rpm so if one could get 1 million
miles on an engine, it would last 2 years...


As far as the generator, I'm Using a Woodward "L series" governor/throttle
body (http://www.woodward.com)  they are not cheap, but do meet the
regulation specs needed to do the job.

Accurate Phase.... Not required, see me privately about this...


Greg




-----Original Message-----
From: gasification-bounces at listserv.repp.org
[mailto:gasification-bounces at listserv.repp.org]On Behalf Of Ken Calvert
Sent: Sunday, February 25, 2007 7:03 PM
To: Gasification
Subject: Re: [Gasification] Wood Gasifier Alaska, Q & A


Greg,
 that is very interesting and obviously 25 years of progress on
what we used to do with two lightbulbs in series accross each phase.
One juggled the throttle until the moment when all the three pairs of bulbs
were out, then you threw the switch!
If they are prepared to let you burn your own power first and then their's
later
that means that you are getting the equivalent of full retail price for your
power! Which is Great!
However, I am guessing that what power you do manage to export will be paid
for by them at a much lower figure?
The next question is,  how do you govern your gas engine accurately enough
to keep exactly in phase
with the grid?  Surely there must be a bit of lag or lead to hold your
generator rather than your gas engine
accurately in phase??
Ken C,   whose living and learning every day!

----- Original Message -----
From: "Greg Manning" <a31ford at inetlink.ca>
To: "Ken Calvert" <renertech at xtra.co.nz>
Sent: Monday, February 26, 2007 12:17 PM
Subject: RE: [Gasification] Wood Gasifier Alaska, Q & A


>
> Greetings Ken...
>
> This is a synchronous setup, not induction (your motor was induction)
> paralleling means that once up to speed, the switchgear "sync's" with the
> line (0 degrees, no lead, no lag, pf of 0.99 ) and the switch performs a
> "closed transition" (three way link, my need for elec, the generator, and
> the grid) the switch can be 4 other ways.
>
> a) open/open/open, nothing connected to nothing.
>
> b) grid/generator/open, Export only of electricity, my need is not
> connected, and I am dark.
>
> c) Grid/open/Me, like a normal grid connection, no generator.
>
> d) open/generator/me generator is ONLY supplying me, no connection to grid
> (mass power failure).
>
> "Closed transition" (Grid,Me,Generator) all three connected, in this mode
> any of the following can be "the connection"
>
> 1) import (generator is not doing anything, OR only supplying a partial
> amount of the total electricity we (I am) using).
>
> 2) export (generator is exporting only, we (I) am using no electricity).
>
> 3) base load (Generator is "base loaded" to a set point, If the set point
> is
> higher then my use, then we are exporting, if it is lower than my use,
> then
> we are importing, BUT in any case, the generator will only put out "X"
> number of watts, no more, no less).
>
> 4) emergency (power failure, generator is my only supply of electricity).
>
>
> The method I will be using is #3 (Base Load), side note #2 is a no no,
> they
> want you to buy your own first..
>
>
> As far as fuel...
>
> I have counted my time and fuel for biomass, BUT only at the "in the yard"
> level, going out and getting a years worth of fuel is like bailing for the
> horses... it simply needs to be done. (the same as if I was using cord
> wood
> to heat).
>
> After the first year, I will have a more accurate cost of "fuel
> included"....
>
>


_______________________________________________
Gasification mailing list
Gasification at listserv.repp.org
http://listserv.repp.org/mailman/listinfo/gasification_listserv.repp.org
http://gasifiers.bioenergylists.org



--
No virus found in this incoming message.
Checked by AVG Free Edition.
Version: 7.5.446 / Virus Database: 268.18.3/700 - Release Date: 2/24/2007
8:14 PM


--
No virus found in this incoming message.
Checked by AVG Free Edition.
Version: 7.5.446 / Virus Database: 268.18.3/700 - Release Date: 2/24/2007
8:14 PM

--
No virus found in this outgoing message.
Checked by AVG Free Edition.
Version: 7.5.446 / Virus Database: 268.18.3/700 - Release Date: 2/24/2007
8:14 PM




More information about the Gasification mailing list