[Strawbale] corner detail problem
Andrew Webb
design at thegreenwebb.com
Wed Jul 5 15:42:58 CDT 2006
Hi ohio,
I'm not sure of the advantage of moving the columns 3' back from the
corners. Can you explain your rationale? The substructure column
positions are already fixed because the footings are poured. It may be
an option to pour additional footings in new positions, but that would
probably cost more than alternatives and be a bit of a waste. The
footings are 2.5m deep concrete piers so not cheap.
-AW
> I was wondering if it would make any sense at all to set the columns three
> feet back from the corner along each wall.