[Strawbale] 5 perms / no ventilation;and top-of-wall
Rob Tom
ArchiLogic at yahoo.ca
Thu Mar 22 15:57:23 CDT 2007
--- In SB-r-us at yahoogroups.com, "N Leone" <nlpub at ...> wrote:
>
> Says the Good Doctor (by way of Mark):
>>>The top seal of the wall needs to be an air barrier,
> and not a vapor barrier. This air barrier can best be formed by straw
> reinforced earth,or a weak mixture of thick lime plaster (applied in
> several layers to avoid cracking). ... >Building paper over a thin
> plaster
> skin would be darn fine.<<
> how do you do that in the case where the tops of the bales are pressing
> up againstfloor joists or truss members?" I don't think you can get
> plaster *under* the joistsor trusses. But if you just plaster between
> the wooden members than you havea nice set of air leakage paths 16 or 24
> inches on center all along your wall.
> And what should you do in the case where the bales run parallel to the
> joistsand you can't really reach the top of the bale at all once its in
> place?
>Page 35 of Issue 34 of The Last Straw shows a top of wall detail that
> Tom Lander used
<snip>
As mentioned earlier in this thread, I haven't had a look at Bruce, King
of Sausalito's latest book and I stopped subscribing to The Last Straw
quite some time ago so I haven't seen Tom's detail and I suppose I really
should have a look at both before commenting but...
I think that there may be some confusion here.
If we are speaking of Cold Climate detailing of the air barrier at the top
of the wall (no matter what the walls are made of) then we are talking
about ensuring continuity of the air barrier at the joint between the wall
plane and the ceiling plane.
In the situation that Ned (who thinks his name is "Nick") mentions where
the joint is inaccessible or difficult to access, then one approach is to
alter the joint (preferably at the design stage) so that it allows one to
make connections (to ensure continuity) at a point that is accessible.
This usually means sketching out the cross section well in advance of
construction so that one has a precise idea of what one is dealing with in
terms of building components, potential air-leakage paths and ideally,
where the dew points are going to be in relation to the air barrier.
As is usually the case, proactively identifying/fixing problems at the
design stage is always better/easier than reactive fixes after the thing
is already built. I realise this may be difficult for those who may be
building for the first time and may not be able to "build the thing in
one's head" first but unfortunately, that is pretty much what needs to be
done.
Ideally, you don't want to have details like the one Ned mentions where
you are trying to create an air seal around framing members that penetrate
the plaster.
Framing members (be they steel or wood) and plaster have different rates
of thermally-induced/change-in-moisture-content-induced
expansion/contraction, so the joint between the dissimilar materials
needs to be able to accommodate movement while still remaining air-tight.
As mentioned earlier, this may be accomplished with flanges and gaskets
but if one has to fit the flanges/gaskets around every framing member
(especially if they're not flat/square) it involves a lot of needless
futzing about.
It's simpler just to move the air barrier to some other location, but
ideally, keeping it to within 1/3 of the total R-value of the cross
section (warm side of) so as to avoid the potential for condensation at
the air barrier just in case one didn't do a very good job of juggling
vapour permeances. (ie How well do *you* know the vapour permeances of all
of the materials that you've used in some assembly ? (Yes, they are
cumulative)).
As a "for instance"-- where joists meet an exterior wall perpendicularly.
Instead of having the rim joist in the knee-jerk typical location at/near
the exterior plane of the wall, think about moving it closer to the
interior plane of the wall (50 mm of end bearing on the wall for wood
joists is more than enough fro mthe joist's point of view) so that
ensuring the continuity of the air barrier would simply mean running a
strip of Tyvek (or similar)around the outside of the rim joist and leaving
flaps to join the upper and lower storey wall or ceiling air barriers.
There are other details WRT the above that need to be dealt with but I
won't go into them here just to avoid any further confusion.
I'm not sure what the context of WatJohn's statement was (quoted at the
opening) so I may be off-base in commenting on that but "straw reinforced
earth" or "weak mixture of lime" doesn't sound right for that joint.
If one has a look at the wall/ceiling joint even in conventional buildings
where the wall & ceiling materials are typically made of the same
materials (ie drywall) and the joint is reinforced with fibreglass mesh or
paper tape, quite often cracks still develop at that joint.
As has been shown on this List and in a piece for The Last Straw (long
ago) on the importance of air-sealing, the volumes of water that are moved
past a crack even as small as 1/16" of an inch in width are significant.
I suppose that it's worth repeating the example for those who are
relatively new to these lists:
===========================================================
Assume: - interior air @ 21 degC and 40% relative humidity
-10 m^2 ceiling of 9 mm board
-2 coats of enamel paint
-crack at edge of ceiling 1.5 mm wide and 1.2 m long
-typical Moosehugger winter conditions WRT outdoor temp and humidity
Water vapour moved by diffusion in 100 days = 3 kg
Water vapour moved by air leakage in 100 days = 20 kg
========================================================
(Source: Builder's Guide to Energy Efficiency in New Housing
Second Edition Jan. 1985
Canadian Home Builders Assoc. )
--
=== * ===
Rob Tom
Kanata, Ontario, Canada
<A r c h i L o g i c at c h a f f y a h o o dot c a >
winnow the chaff from my edress in your reply