At 07:04 PM 12/30/2007, John Paul Ogden wrote:
>"Of course, the lack of cracking is due in part to proper preparation
>of the sub-strate."
>
>Do you have the details as to how you dealt with the substrate properly?
>I've often wondered what is the best way to deal with preparing the
>substrate.
Others have described it better, but the two things which I did were
as follows:
1 - Don't dig it up. Leave undisturbed soil. Where you must, like
to put in sewer pipes, use a jumping jack tamper, small lifts and
wetting to re-compact the soil.
2 - Put down a layer of sand over the substrate, and tamp it with a
vibrating compacter to get it absolutely flat.